The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Rawthorpe Lane. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January.
Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !
Monday, 23 December 2013
Friday, 20 December 2013
Externally it is
mission accomplished with us laying the tarmac base course. All the edgings and
kerbs are in ready for the block paving to start in the new
year. Internally we have
laid the vinyl flooring to the plots in Block 1 with only the communals to
complete. Blocks 2, 3 and 4 are complete with just some fine tuning to be
done.
All remains is to
wish you all a Merry Christmas and a Happy New Year from all the site
staff.
Monday, 18 November 2013
Externally we have
completed the installation of the services allowing us to continue with kerbing,
block paving and flagging in front of blocks 2, 3 and 4. Internally all the
kitchens and bathrooms are installed. We are snagging and final decorating in
blocks 2 and 3. In block 1 we have hung the doors and
are continuing into block 4 next week.
Friday, 18 October 2013
Externally British
Gas have laid the last of the mains, service pipe and meters. Northern Power
Grid have assured us the plots will be connected next week. Block 1 is
progressing well, we have tiled the bathrooms and kitchens and the 2/3rd
fix M&E is also continuing. Joiners are coming through fixing skirting and
architraves. In Block 4 all kitchens
are installed and the tiler has started. Next week the electricians will
commence 2nd fixing.
Friday, 11 October 2013
Externally we
completed the laying of the water pipes from the plots and Yorkshire Water
connected them to the manifolds. We are continuing
with the BT and electric service ducts. Internally in Block
1 all the kitchens are installed and we are continuing tiling following on with
2nd fix electrical fixing the switches and sockets. In Block 4
plastering is complete. The 2nd fix plumbing to the kitchens has been done and
the kitchens units are been installed. In Blocks 2 and
3 are awaiting the power to be connected so we can do the final snag and
decorating.
Friday, 4 October 2013
Friday, 21 June 2013
Friday, 14 June 2013
Monday, 10 June 2013
Monday, 3 June 2013
Wednesday, 29 May 2013
Following the insulating and screeding of the floor at Block 1, the timber sole plates are being fixed in position, ready to receive the Timber Frame.
The lower level of the scaffold is being erected around the block to allow for access when lifting the timber frame in.
Meanwhile on blocks 2 and 3 where the timber frame is up, the bricklayers are beginning to wall externally.
Monday, 20 May 2013
Tuesday, 14 May 2013
The splash course is laid on a gas membrane (yellow) to prevent gasses rising up into the home. This splash course will later support the timber frame sole plates.
Block 2 timber frame is erected and both roofs are on so internal works can begin with insulation.
The Sarnafil roof covering is being installed at Block 3, the single ply membrane gives a very smooth finish.
Tuesday, 7 May 2013
The Beam and Block flooring is installed on Block 1, the blocks help to evenly distribute the beams that support them, which span the substructure walls.
Timber frame is erected at Block 2 and the ply is begun on the roof ready for the installation of the Sarnafil membrane roof covering.
Inside block 2 we can see the timber panels which arrive on site with rigid insulation already fitted which will ensure the homes will have excellent thermal performance.
Roof trusses are assembled on the substructure of Block 3 inside the scaffolding to save space on site, these will then be lifted onto the neighbouring plot.
Friday, 26 April 2013
Wednesday, 24 April 2013
Friday, 19 April 2013
Tuesday, 16 April 2013
Wednesday, 10 April 2013
The retaining wall on block 4 has begun. This section is created using shuttering on both sides (shuttering is shown here with the red edge) with the concrete poured between, when cured the shuttering will be removed.
Scaffolding is being erected around block 3 in preparation for the arrival of the timber frame.
Foundations are poured at the back of the Block 1 retaining wall ready for the block work to be built up.
Monday, 8 April 2013