Externally British
Gas have laid the last of the mains, service pipe and meters. Northern Power
Grid have assured us the plots will be connected next week. Block 1 is
progressing well, we have tiled the bathrooms and kitchens and the 2/3rd
fix M&E is also continuing. Joiners are coming through fixing skirting and
architraves. In Block 4 all kitchens
are installed and the tiler has started. Next week the electricians will
commence 2nd fixing.