Externally we have
completed the installation of the services allowing us to continue with kerbing,
block paving and flagging in front of blocks 2, 3 and 4. Internally all the
kitchens and bathrooms are installed. We are snagging and final decorating in
blocks 2 and 3. In block 1 we have hung the doors and
are continuing into block 4 next week.



No comments:
Post a Comment
Note: only a member of this blog may post a comment.