Following the insulating and screeding of the floor at Block 1, the timber sole plates are being fixed in position, ready to receive the Timber Frame.
The lower level of the scaffold is being erected around the block to allow for access when lifting the timber frame in.
Meanwhile on blocks 2 and 3 where the timber frame is up, the bricklayers are beginning to wall externally.