Friday, 11 October 2013

Externally we completed the laying of the water pipes from the plots and Yorkshire Water connected them to the manifolds. We are continuing with the BT and electric service ducts. Internally in Block 1 all the kitchens are installed and we are continuing tiling following on with 2nd fix electrical fixing the switches and sockets. In Block 4 plastering is complete. The 2nd fix plumbing to the kitchens has been done and the kitchens units are been installed. In Blocks 2 and 3 are awaiting the power to be connected so we can do the final snag and decorating.