Friday, 4 October 2013


A good week which saw us strip the scaffolding to block 1 and 4.  This will enable us to start installing the services.

Internally in block 1 we started installing kitchens to the 2nd floor and continuing 2nd fix M&E and mist coating the walls.

In block 4 we have completed the 1st M&E and are closing up the walls and starting plastering.