Friday, 31 January 2014

Now the tarmac has been laid the site looks complete. All that remains to be done is the planting and the snagging. Internally Kirklees Council are undertaking their final inspections before the planned handover date of February 13th.







Monday, 23 December 2013

The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Rawthorpe Lane. Our site will close for the Christmas period on Tuesday  24 December, and will re-open in the New Year on Thursday 2 January.

Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !

Friday, 20 December 2013

Externally it is mission accomplished with us laying the tarmac base course. All the edgings and kerbs are in ready for the block paving to start in the new year. Internally we have laid the vinyl flooring to the plots in Block 1 with only the communals to complete. Blocks 2, 3 and 4 are complete with just some fine tuning to be done.
 

All remains is to wish you all a Merry Christmas and a Happy New Year from all the site staff.



Monday, 18 November 2013

Externally we have completed the installation of the services allowing us to continue with kerbing, block paving and flagging in front of blocks 2, 3 and 4. Internally all the kitchens and bathrooms are installed. We are snagging and final decorating in blocks 2 and 3. In block 1 we have hung the doors and are continuing into block 4 next week.




Friday, 18 October 2013

Externally British Gas have laid the last of the mains, service pipe and meters. Northern Power Grid have assured us the plots will be connected next week. Block 1 is progressing well, we have tiled the bathrooms and kitchens and the 2/3rd fix M&E is also continuing. Joiners are coming through fixing skirting and architraves. In Block 4 all kitchens are installed and the tiler has started. Next week the electricians will commence 2nd fixing.


Friday, 11 October 2013

Externally we completed the laying of the water pipes from the plots and Yorkshire Water connected them to the manifolds. We are continuing with the BT and electric service ducts. Internally in Block 1 all the kitchens are installed and we are continuing tiling following on with 2nd fix electrical fixing the switches and sockets. In Block 4 plastering is complete. The 2nd fix plumbing to the kitchens has been done and the kitchens units are been installed. In Blocks 2 and 3 are awaiting the power to be connected so we can do the final snag and decorating.




Friday, 4 October 2013


A good week which saw us strip the scaffolding to block 1 and 4.  This will enable us to start installing the services.

Internally in block 1 we started installing kitchens to the 2nd floor and continuing 2nd fix M&E and mist coating the walls.

In block 4 we have completed the 1st M&E and are closing up the walls and starting plastering.