Now the tarmac has
been laid the site looks complete. All that remains to be done is the planting and
the snagging. Internally Kirklees Council are undertaking their final inspections before the planned handover date of February 13th.
Friday, 31 January 2014
Monday, 23 December 2013
The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Rawthorpe Lane. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January.
Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !
Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !
Friday, 20 December 2013
Externally it is
mission accomplished with us laying the tarmac base course. All the edgings and
kerbs are in ready for the block paving to start in the new
year. Internally we have
laid the vinyl flooring to the plots in Block 1 with only the communals to
complete. Blocks 2, 3 and 4 are complete with just some fine tuning to be
done.
All remains is to
wish you all a Merry Christmas and a Happy New Year from all the site
staff.
Monday, 18 November 2013
Externally we have
completed the installation of the services allowing us to continue with kerbing,
block paving and flagging in front of blocks 2, 3 and 4. Internally all the
kitchens and bathrooms are installed. We are snagging and final decorating in
blocks 2 and 3. In block 1 we have hung the doors and
are continuing into block 4 next week.
Friday, 18 October 2013
Externally British
Gas have laid the last of the mains, service pipe and meters. Northern Power
Grid have assured us the plots will be connected next week. Block 1 is
progressing well, we have tiled the bathrooms and kitchens and the 2/3rd
fix M&E is also continuing. Joiners are coming through fixing skirting and
architraves. In Block 4 all kitchens
are installed and the tiler has started. Next week the electricians will
commence 2nd fixing.
Friday, 11 October 2013
Externally we
completed the laying of the water pipes from the plots and Yorkshire Water
connected them to the manifolds. We are continuing
with the BT and electric service ducts. Internally in Block
1 all the kitchens are installed and we are continuing tiling following on with
2nd fix electrical fixing the switches and sockets. In Block 4
plastering is complete. The 2nd fix plumbing to the kitchens has been done and
the kitchens units are been installed. In Blocks 2 and
3 are awaiting the power to be connected so we can do the final snag and
decorating.