Friday, 18 October 2013

Externally British Gas have laid the last of the mains, service pipe and meters. Northern Power Grid have assured us the plots will be connected next week. Block 1 is progressing well, we have tiled the bathrooms and kitchens and the 2/3rd fix M&E is also continuing. Joiners are coming through fixing skirting and architraves. In Block 4 all kitchens are installed and the tiler has started. Next week the electricians will commence 2nd fixing.


Friday, 11 October 2013

Externally we completed the laying of the water pipes from the plots and Yorkshire Water connected them to the manifolds. We are continuing with the BT and electric service ducts. Internally in Block 1 all the kitchens are installed and we are continuing tiling following on with 2nd fix electrical fixing the switches and sockets. In Block 4 plastering is complete. The 2nd fix plumbing to the kitchens has been done and the kitchens units are been installed. In Blocks 2 and 3 are awaiting the power to be connected so we can do the final snag and decorating.




Friday, 4 October 2013


A good week which saw us strip the scaffolding to block 1 and 4.  This will enable us to start installing the services.

Internally in block 1 we started installing kitchens to the 2nd floor and continuing 2nd fix M&E and mist coating the walls.

In block 4 we have completed the 1st M&E and are closing up the walls and starting plastering.