Gas have laid the last of the mains, service pipe and meters. Northern Power
Grid have assured us the plots will be connected next week. Block 1 is
progressing well, we have tiled the bathrooms and kitchens and the 2/3rd
fix M&E is also continuing. Joiners are coming through fixing skirting and
architraves. In Block 4 all kitchens
are installed and the tiler has started. Next week the electricians will
commence 2nd fixing.
Friday, 18 October 2013
Friday, 11 October 2013
Externally we
completed the laying of the water pipes from the plots and Yorkshire Water
connected them to the manifolds. We are continuing
with the BT and electric service ducts. Internally in Block
1 all the kitchens are installed and we are continuing tiling following on with
2nd fix electrical fixing the switches and sockets. In Block 4
plastering is complete. The 2nd fix plumbing to the kitchens has been done and
the kitchens units are been installed. In Blocks 2 and
3 are awaiting the power to be connected so we can do the final snag and
decorating.