The Wates team and our sub-contractors would like to thank you for your continued patience whilst we have been on site at Rawthorpe Lane. Our site will close for the Christmas period on Tuesday 24 December, and will re-open in the New Year on Thursday 2 January.
Can we also take this opportunity to wish you a Merry Christmas and a Happy New Year !
Monday, 23 December 2013
Friday, 20 December 2013
Externally it is
mission accomplished with us laying the tarmac base course. All the edgings and
kerbs are in ready for the block paving to start in the new
year. Internally we have
laid the vinyl flooring to the plots in Block 1 with only the communals to
complete. Blocks 2, 3 and 4 are complete with just some fine tuning to be
done.
All remains is to
wish you all a Merry Christmas and a Happy New Year from all the site
staff.