Monday, 25 February 2013
Construction of the retaining wall on the lower level of Block 1 has now commenced.
Started back fill of the ground beams on Block 2 and Block 3 ready for masonry works to commence.
Friday, 22 February 2013
The pre-cast ground beams have now been installed on Blocks 2 and 3.
Tuesday, 19 February 2013
Excavations for the foundations are now complete and we started concreting the trenches Block 1.
Wednesday, 13 February 2013
Excavation works have been carried out for the foundations on Blocks 1 & 4. Next we will excavate out for the foundations.
Blocks 2 & 3 are being prepared by the groundworker’s to receive pre-cast ground beams